C-17 Lot III Production Contract

NSIAD-93-301R: Published: Sep 24, 1993. Publicly Released: Oct 25, 1993.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Pursuant to a congressional request, GAO provided information on the estimated cost for the Air Force's C-17 lot III production contract, focusing on: (1) the Defense Plant Representative Office's (DPRO) basis for modifying its original cost estimate; and (2) whether C-17 contract costs will exceed the contract ceiling price. GAO found that: (1) DPRO originally estimated that the C-17 contract would exceed the contract ceiling price; (2) DPRO has revised its original cost estimate and reallocated disputed engineering costs from the production contract to the development contract; (3) the DPRO modification is reasonable and consistent with its position that engineering costs should be charged to the development contract; (4) C-17 contract costs are likely to exceed the contract ceiling price due to inadequate contract performance; and (5) DPRO is concerned about several contract practices that could obscure and delay the timely reporting of negative cost performance data.

Sep 22, 2016

Sep 21, 2016

Sep 19, 2016

Sep 12, 2016

Sep 8, 2016

Sep 7, 2016

Sep 6, 2016

Aug 25, 2016

Looking for more? Browse all our products here