Navy Ships:

Problems Continue to Plague the Seawolf Submarine Program

NSIAD-93-171: Published: Aug 4, 1993. Publicly Released: Aug 10, 1993.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

GAO reviewed the Navy's Seawolf (SSN-21) Class Nuclear-Powered Attack Submarine construction program, focusing on: (1) the change in the status of the class design and SSN-21 construction since December 1991; (2) the effectiveness of technical and management actions to resolve lead submarine welding problems and guard against a recurrence of a similar problem in the future; and (3) Navy efforts to control schedule delays.

GAO found that: (1) SSN-21 construction has fallen at least 5 months behind schedule; (2) factors contributing to construction delays include late drawings and other design data, insufficient staff and problems preparing and releasing the instructions and materials needed for construction, and a smaller-than-expected SSN-21 construction work force; (3) 5 percent of the work packages scheduled for completion and 9 percent of the completed work packages scheduled for release to construction workers were delinquent; (4) the incompatibility between the design and construction schedules could further delay SSN-21 delivery; (5) it will cost $683 million to design the SSN-21 class, which is 125 percent over the original contract cost estimate; (6) cost increases are primarily due to changes in specifications, reductions in the number of submarines to be constructed, and the re-estimation of construction elements; and (7) the contractor has corrected the welding problems and instituted new welding procedures to prevent any recurrence of similar problems.

Oct 20, 2014

Oct 9, 2014

Oct 8, 2014

Oct 2, 2014

Sep 30, 2014

Sep 26, 2014

Sep 25, 2014

Sep 19, 2014

Looking for more? Browse all our products here