Strategic Defense Initiative Program:

Basis for Reductions in Estimated Cost of Phase I

NSIAD-90-173: Published: May 9, 1990. Publicly Released: May 10, 1990.

Additional Materials:


Office of Public Affairs
(202) 512-4800

Pursuant to a congressional request, GAO reviewed the Strategic Defense Initiative Organization's (SDIO) reasons for reducing its cost estimate for the Phase 1 Strategic Defense System, and the credibility of its October 1988 estimate of $69.1 billion.

GAO found that: (1) SDIO appropriately prepared the October 1988 cost estimate, but made errors that understated the cost by $2.1 billion; (2) SDIO relied on overly optimistic assumptions, resulting in an understatement of at least $5 billion; (3) the $19.3-billion reduction in estimated Phase 1 costs was due to a quantity reduction, a change in technical characteristics and the cost estimate models, and a reduction in support costs; and (4) SDIO deferred development costs to subsequent programs, resulting in a $2-billion reduction in support costs.

Oct 20, 2016

Oct 17, 2016

Oct 12, 2016

Sep 26, 2016

Sep 22, 2016

Sep 21, 2016

Sep 19, 2016

Looking for more? Browse all our products here