Strategic Defense Initiative Program:

Basis for Reductions in Estimated Cost of Phase I

NSIAD-90-173: Published: May 9, 1990. Publicly Released: May 10, 1990.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Pursuant to a congressional request, GAO reviewed the Strategic Defense Initiative Organization's (SDIO) reasons for reducing its cost estimate for the Phase 1 Strategic Defense System, and the credibility of its October 1988 estimate of $69.1 billion.

GAO found that: (1) SDIO appropriately prepared the October 1988 cost estimate, but made errors that understated the cost by $2.1 billion; (2) SDIO relied on overly optimistic assumptions, resulting in an understatement of at least $5 billion; (3) the $19.3-billion reduction in estimated Phase 1 costs was due to a quantity reduction, a change in technical characteristics and the cost estimate models, and a reduction in support costs; and (4) SDIO deferred development costs to subsequent programs, resulting in a $2-billion reduction in support costs.

Mar 2, 2015

Feb 26, 2015

Feb 24, 2015

Feb 18, 2015

Feb 11, 2015

Jan 29, 2015

Jan 27, 2015

Jan 21, 2015

Looking for more? Browse all our products here