Torpedo Procurement:

Issues Related to the Navy's MK-50 Torpedo Propulsion System

NSIAD-89-8: Published: Jan 27, 1989. Publicly Released: Feb 2, 1989.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In response to a congressional request, GAO reviewed the Navy's procurement of MK-50 torpedo propulsion components, to determine: (1) whether the Navy would save money if it procured the propulsion components separately and provided them to the prime contractor as government-furnished equipment (GFE); (2) when the Navy should implement such a strategy; and (3) whether providing prime contractors with the components would affect the torpedo warranty.

GAO found that: (1) although it would be possible to test an alternative procurement strategy before full-rate production, such a substantive change could delay production with no assurance of cost savings; (2) the Navy believed that its procurement strategy was the most cost-effective, since the prime contractors would buy parts from their suppliers, the Navy would procure the spare parts separately, and technology transfer was expected to continue through initial production; (3) the component suppliers would have to warrant components supplied as GFE, but the prime contractors would have to warrant installation and modification of GFE; and (4) the most appropriate time for the Navy to choose a procurement strategy would be the beginning of competition for full-rate production.

Sep 22, 2016

Sep 21, 2016

Sep 19, 2016

Sep 12, 2016

Sep 8, 2016

Sep 7, 2016

Sep 6, 2016

Aug 25, 2016

Looking for more? Browse all our products here