U.S. Embassy, Moscow:

Why Construction Took Longer and Cost More Than Anticipated

NSIAD-88-23: Published: Oct 23, 1987. Publicly Released: Nov 30, 1987.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In response to a congressional request, GAO reviewed the Department of State's efforts to construct U.S. embassy facilities in Moscow.

GAO found that: (1) as of March 1987, Congress had appropriated $192 million for the construction, of which State has obligated about $146 million and expended about $137 million; (2) there were 80 modifications to contracts awarded to U.S. firms under the project, resulting in an increase of about $10.9 million over the original price; (3) the increased construction costs were due to inflation, increased project requirements, changes in facility security, and delays by the Soviet contractor; and (4) security enhancement revisions were the most costly changes. GAO also found that the Soviet contractor: (1) lacked sufficient skilled craftsmen; (2) was unable to timely provide necessary building materials; (3) failed to properly prepare the site; and (4) failed to follow the construction schedule. GAO noted that work at the U.S. embassy is at a standstill, pending the outcome of U.S. security reviews.

Sep 28, 2016

Sep 27, 2016

Sep 22, 2016

Sep 20, 2016

Sep 7, 2016

Aug 31, 2016

Aug 25, 2016

Aug 15, 2016

Looking for more? Browse all our products here