Space Shuttle:

NASA's Major Changes to Flight Hardware

NSIAD-88-173FS: Published: Jun 27, 1988. Publicly Released: Jul 6, 1988.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In response to a congressional request, GAO identified the types of changes that the National Aeronautics and Space Administration (NASA) made to the space shuttle's flight hardware, focusing on enhancements: (1) it made to flight hardware; (2) that cost at least $5 million each; and (3) it implemented from 1981 through 1987.

GAO found that NASA: (1) made 56 changes to the space shuttle; (2) initiated 31 changes before the Challenger accident and 25 after the accident; (3) budgeted about $403 million in three increments through 1993; (4) awarded a $198.2 million development contract for the first increment; and (5) estimated that the cost of the changes would total about $2.4 billion. GAO also found that the primary justifications for making the changes included: (1) studies which evaluated existing system designs; (2) the high costs of repairing outdated equipment; (3) improving the reliability of existing components; (4) demonstrating and improving component capabilities; (5) correcting components that were not fully functioning as designed or as necessary; (6) replacing obsolete parts; and (7) increasing safety.

Dec 15, 2014

Dec 10, 2014

Dec 9, 2014

Jul 23, 2014

Jul 16, 2014

Jun 20, 2014

May 15, 2014

May 8, 2014

Apr 15, 2014

Looking for more? Browse all our products here