Quality Assurance:

Concerns About Four Navy Missile Systems

NSIAD-88-104, Mar 24, 1988

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In response to a congressional request, GAO reviewed quality assurance problems on four missile systems, the Phoenix, the Harpoon, the Sparrow, and the High-Speed Anti-Radiation (HARM) missiles, to determine the causes and potential effects of the problems.

GAO found that: (1) all the missiles it examined had defects, since they did not completely conform to contract specifications; (2) some defects occurred because of the prime contractor's inadequate manufacturing processes, but subcontractors' poor manufacturing and inadequate quality oversight caused more significant problems; and (3) contractors believed that many of the reported manufacturing defects in soldering were due to the Navy's stringent soldering specifications. GAO believes that the Navy should have: (1) tighter controls over subcontractor production; (2) better reporting of changes in manufacturing processes; and (3) its prime contractors inspect and test subcontractor-manufactured items.

Apr 17, 2013

Feb 7, 2013

Dec 3, 2012

Nov 19, 2012

Jun 27, 2012

Jun 20, 2012

Jun 6, 2012

Mar 28, 2012

Looking for more? Browse all our products here