Battlefield Automation: Army Air Defense Command and Control System Acquisition and Budget Issues

NSIAD-87-208 Published: Sep 28, 1987. Publicly Released: Sep 28, 1987.
Jump To:
Skip to Highlights

Highlights

In response to a congressional request, GAO reviewed the Army's Forward Area Air Defense Command, Control and Intelligence System (FAAD C2I) focusing on the system's cost, schedule and performance, and the Army's 1988 budget request.

Recommendations

Matter for Congressional Consideration

Matter Status Comments
The House Committee on Appropriations, Subcommittee on Defense, should reduce the Army's FY 1988 FAAD C2I funding request by $93.2 million.
Closed – Implemented
The Joint Conference Committee deleted the Army's FY 1988 budget request of $93.2 million for the FAAD C2 System.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of the Army The Secretary of the Army should review the decision to exclude certain requirements when estimating the FAAD C2I program cost.
Closed – Implemented
The Joint Conference Committee deleted the Army's FY 1988 budget request of $93.2 million for the FAAD C2 System.
Department of the Army The Secretary of the Army should direct the project office to include all valid requirements in subsequent cost estimates.
Closed – Implemented
The Joint Conference Committee deleted the Army's FY 1988 budget request of $93.2 million for the FAAD C2 System.