Contract Pricing:

Subcontractor Prices Overstated on AN/TSQ-111 Communications Contract

NSIAD-86-166: Published: Aug 22, 1986. Publicly Released: Aug 22, 1986.

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

GAO reviewed whether a contractor provided accurate, complete, and current cost or pricing data for selected subcontracted items on communications equipment contracts.

GAO noted that the Air Force and the contractor agreed to a contract price for a production program and, as a result, the contractor certified that the cost data for the contract was accurate, complete, and current; however, the contractor did not submit accurate or current data for the parts it purchased from seven subcontractors. GAO found that: (1) the contractor overstated the prices for five subcontractors and understated the prices for two other subcontractors, which resulted in a $962,192 cost overstatement; (2) the overstatement was a result of contractor errors and omissions in the data it submitted to the government; (3) the contractor did not provide certain cost and pricing data to the contracting officer before the close of prime-contract negotiations; and (4) the option buys included similarly overstated costs for parts.

Mar 27, 2014

Mar 13, 2014

Mar 12, 2014

Feb 27, 2014

Dec 23, 2013

Dec 16, 2013

Dec 12, 2013

Dec 11, 2013

Looking for more? Browse all our products here