Savings on the CVN-71 and Termination Cost of the CVN-72 and -73 Nuclear Aircraft Carriers

NSIAD-83-16: Published: Jul 21, 1983. Publicly Released: Aug 22, 1983.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In response to a congressional request, GAO reviewed the Navy's programs to acquire the CVN-71, -72, and -73 nuclear aircraft carriers.

GAO determined that the Navy's estimated savings of about $74 million on the CVN-71 appears reasonable if the incentive delivery date of December 31, 1986, is met. GAO noted that the CVN-71 is currently on schedule to meet that date. GAO found that the Navy has not made a detailed analysis of the cost to terminate procurement of the CVN-72 and CVN-73. However, the Navy stated that the cost to cancel one carrier would probably be in excess of $1.5 billion and that such action would cause claim and counterclaim litigation.

Sep 20, 2016

Sep 6, 2016

Aug 19, 2016

Aug 12, 2016

Jul 29, 2016

Jul 28, 2016

Jul 13, 2016

Jul 11, 2016

Jun 13, 2016

Looking for more? Browse all our products here