Tactical Operations System Development Program Should Not Continue as Planned

LCD-80-17: Published: Nov 20, 1979. Publicly Released: Nov 20, 1979.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

For 20 years the Army has been trying to develop a system that would use automation to assist battlefield commanders in making tactical command and control decisions. The current development of the Tactical Operations System (TOS), begun as a test bed in 1971, has not been very successful, because the Army overlooked key aspects of sound system management.

The Army has had more than sufficient time to implement sound management and system development practices. It seems that the TOS program will be forever evolving if information requirements are not clearly defined before proceeding with development. Plans to continue development by fielding one system in Europe will require over $100 million in additional funding. At best, this interim system can be expected to be rendered inadequate by corps-level requirements and system development efforts. Because the corps-level system presents an opportunity to provide a full identification of requirements and state-of-the-art technology, little would be gained from a developmental point of view by continuing with the division-level development effort at this time. Although there is a need for automated assistance to support command and control, it is the opinion of GAO that the Army is not in a position to make major commitments to division TOS. Since the ongoing corps-level study is intended to provide the design needed, the Army should not make investments in hardware or software until these requirements are known and the system design is established.

Recommendation for Executive Action

  1. Status: Closed

    Comments: Please call 202/512-6100 for additional information.

    Recommendation: The Secretary of Defense should direct the Secretary of the Army to delay the division TOS development effort until the results of the master plan and corps studies are known. If division TOS meets the needs of that automation architecture, the Secretary of Defense should direct the Secretary of the Army to make a technical and cost trade-off analysis of continuing with the current division TOS effort. The Secretary of Defense should also direct the Secretary of the Army to delay further experimentation with hardware and software for the corps-level TOS until the results of ongoing studies are known.

    Agency Affected:

 

Explore the full database of GAO's Open Recommendations »

Sep 28, 2016

Sep 27, 2016

Sep 26, 2016

Sep 23, 2016

Sep 21, 2016

Sep 7, 2016

Aug 30, 2016

Aug 11, 2016

Jul 22, 2016

Looking for more? Browse all our products here