Projected dollar and manpower reductions in the depot maintenance area have prompted the Air Force to study possible ways of reducing costs without decreasing support capability. The Air Force decided that the best means to reduce maintenance costs while insuring high usage of depot maintenance facilities and capabilities was to redistribute the depot-level maintenance workload by technology rather than by a weapons system. This redistribution, which concentrates the workload into a single repair facility when items require similar skills, equipment, and facilities in the repair process, is called the technology repair center concept.

The Air Force recognized the need for operational change and developed the proper mechanics for planning it. However, the benefit-cost projections used to justify the technology repair center concept may be questionable because: (1) the depot maintenance cost accounting system could not provide adequate data on Air Logistics Center maintenance operations; (2) the audit trail was insufficient to verify some benefits; and (3) the tracking mechanism used could not isolate benefits and costs attributable to the technology repair center concept from other ongoing projects. Due to these limitations, a precise evaluation of the claimed benefits and costs was impracticable.

Recommendation for Executive Action

  1. Status: Closed

    Comments: Please call 202/512-6100 for additional information.

    Recommendation: In view of the new, cost-saving initiatives under consideration by the Department of Defense, the Secretary of Defense should, for future operational or organizational changes, insure that: (1) the services' cost accounting systems can provide adequate data on depot operations for making valid benefit-cost comparisons; (2) adequate benefit-cost audit trails are established; and (3) the tracking system used can isolate benefits and costs associated with the change from those of other ongoing projects.

    Agency Affected:

 

Explore the full database of GAO's Open Recommendations »

Sep 22, 2016

Sep 21, 2016

Sep 19, 2016

Sep 12, 2016

Sep 8, 2016

Sep 7, 2016

Sep 6, 2016

Aug 25, 2016

Looking for more? Browse all our products here