Military Space Operations:

Shuttle and Satellite Computer Systems Do Not Meet Performance Objectives

IMTEC-88-7: Published: Aug 5, 1988. Publicly Released: Aug 5, 1988.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In response to a congressional request, GAO reviewed the: (1) status, current plans, and supporting studies for the Air Force's Consolidated Space Operations Center; and (2) Air Force's long-range plans for computer and communications systems architecture to support satellite control.

GAO found that: (1) the Air Force did not meet its operational schedule estimates for the Center; (2) the Air Force expects to spend $1.85 billion, three times its original estimate, for new satellite control capabilities; (3) performance problems delayed transition of the systems to operational status; (4) future satellite control operations would require improved survivability and increased capacity and efficiency; (5) the Air Force was studying a new system architecture concept that would require more on-board satellite data processing to reduce reliance on ground facilities and would cost an estimated $48 billion; and (6) this concept would require development of a comprehensive plan specifying long-range goals, objectives, capabilities, and costs. GAO also found that, due to a congressional budget reduction of $29 million for the Center, the Department of Defense cancelled a planned shuttle complex at the Center.

Oct 4, 2017

Sep 18, 2017

Sep 6, 2017

Jul 13, 2017

Jun 21, 2017

Jun 13, 2017

May 18, 2017

May 15, 2017

Apr 11, 2017

Looking for more? Browse all our products here