Navy Office Space:

Cost Estimate for Consolidating the Naval Systems Commands May Be High

GGD-91-61: Published: Mar 8, 1991. Publicly Released: Mar 8, 1991.

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Pursuant to a congressional request, GAO reviewed the General Services Administration's (GSA) cost estimates for consolidating Naval Systems Commands offices in a single facility in northern Virginia.

GAO found that: (1) GSA estimated that it would cost $273.8 million to construct 1 million square feet of occupiable space; (2) the GAO construction cost estimate was $34.8 million lower than the GSA estimate, but the GAO land cost estimate was $19.3 million higher; (3) the reasons for differences between GAO and GSA estimates included different definitions of occupiable space, inflation, and different unit costs; (4) GSA cost estimates for 10 recent construction projects following a similar estimating process as the Navy project were 9 percent higher overall than the eventual contract awards; (5) the GSA estimated cost per square foot exceeded its general cost guidelines; (6) real estate development market conditions could result in offerors accepting lower than normal overhead costs and profits; and (7) project costs could be reduced if GSA used value engineering.

Aug 7, 2014

Jul 30, 2014

Jul 29, 2014

Jul 22, 2014

Jun 17, 2014

Jun 11, 2014

Jun 10, 2014

May 28, 2014

May 21, 2014

May 12, 2014

Looking for more? Browse all our products here