Resolution Trust Corporation:

Unnecessary Loan Servicing Costs Due to Inadequate Contract Oversight

GGD-91-19: Published: Jan 17, 1991. Publicly Released: Jan 17, 1991.

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Pursuant to a congressional request, GAO reviewed the Resolution Trust Corporation's (RTC) use of interim servicing agreements (ISA) to determine ISA loan servicing costs and the adequacy of RTC monitoring of such agreements.

GAO found that: (1) RTC could have avoided as much as $1 million in loan processing costs by closing one large loan processing center; (2) unnecessary costs resulted from inadequate contract monitoring, insufficient RTC and contractor oversight, insufficient cost information, and RTC failure to take early action to market the center; (3) RTC did not have enough staff to adequately oversee center operations to ensure that costs incurred were reasonable; and (4) RTC did not begin marketing the center until 6 months after 85 percent of the center's loans had been removed.

Sep 29, 2017

Sep 12, 2017

Sep 7, 2017

Apr 19, 2017

Mar 29, 2017

Feb 24, 2017

Dec 29, 2016

Dec 15, 2016

Nov 15, 2016

Looking for more? Browse all our products here