Nuclear Waste:

DOE Needs to Improve Cost Estimates for Transuranic Waste Projects at Los Alamos

GAO-15-182: Published: Feb 18, 2015. Publicly Released: Mar 23, 2015.

Additional Materials:

Contact:

David C. Trimble
(202) 512-3841
trimbled@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

What GAO Found

The National Nuclear Security Administration's (NNSA) project to remove transuranic (TRU) waste—primarily discarded equipment and soils contaminated with certain radioactive material—at Los Alamos National Laboratory (LANL) did not meet its cost estimates. At the end of fiscal year 2014, NNSA had spent about $931 million on the project, exceeding its 2006 estimate of $729 million by $202 million. Under current plans, the project is also expected to exceed its 2009 estimate. NNSA did not meet its cost estimates, in part, because they were based on aggressive funding assumptions designed to meet the completion dates agreed to in a 2005 cleanup agreement, which the Department of Energy (DOE) did not fully fund. At the time of GAO's review, NNSA was developing a new project completion cost estimate of about $1.6 billion, with completion projected for October 2022. NNSA had not revised the project's cost estimate since 2009 because the agency was reluctant to approve an estimate with a completion date that conflicted with the 2005 cleanup agreement. However, according to an NNSA official, NNSA's new estimate may not reflect current conditions—partly because of uncertainty created by funding and the indefinite suspension of shipments of TRU waste to the permanent repository at DOE's Waste Isolation Pilot Plant (WIPP) after a radioactive release closed WIPP in February 2014. By revising the estimate to include the current understanding of project conditions, including the uncertainty at WIPP, NNSA program managers can, for example, more accurately identify cost overruns.

NNSA's cost estimate for the TRU Waste Facility (TWF), which consisted of separate cost estimates for completing construction and for operations and maintenance, partially reflected each of the four characteristics of a reliable estimate (comprehensive, well-documented, accurate, and credible) as established by best practices. For example, NNSA's estimate was partially well-documented by clearly documenting the data sources and methodology used to develop the construction estimate. However, NNSA did not sufficiently document the approach used to develop the operations and maintenance estimate, which represented about 74 percent of the TWF's life-cycle costs, because DOE's project management order does not require these costs to be documented when a project is approved to request funding from Congress for construction. As a result, GAO could not determine whether the cost-estimating approach was appropriate. In addition, NNSA's estimate was partially credible because NNSA completed an independent cost estimate (ICE) that provided an unbiased cross-check of the construction estimate consistent with best practices, but it did not include the operations and maintenance costs in the ICE because it was not required by DOE's project management order. Moreover, NNSA did not conduct a sensitivity analysis to quantify variations in the TWF's cost estimates due to changes in key assumptions because it was not required by DOE, which also affected the estimate's credibility. Doing a sensitivity analysis increases the chance that decisions for the TWF will focus on the elements that have the greatest effect on cost, according to best practices. Updating the TWF's cost estimate to include all life-cycle costs and needed analyses, would provide NNSA more reliable information for better managing the TWF as it prepares for the start of operations, which NNSA expects could be as early as April 2016.

Why GAO Did This Study

Nuclear weapons activities at LANL have generated large quantities of TRU waste that must be disposed of properly. To address a 2005 cleanup agreement with the state of New Mexico requiring DOE to close LANL's TRU waste site, NNSA is to oversee two TRU waste projects. The first is to remove the waste stored at LANL and ship it to WIPP for permanent disposal. The second is to construct a facility—the TWF—to provide new capabilities for managing newly generated TRU waste at LANL. NNSA has developed cost estimates for both projects.

GAO was asked to review cost estimates for the TRU waste projects at LANL. This report examines (1) the extent to which NNSA's TRU waste removal project at LANL has met its cost estimates and (2) the extent to which NNSA's cost estimate for the TWF met best practices for a reliable estimate. GAO reviewed spending data for the TRU waste removal project for fiscal years 2006 through 2014 and the cost estimates for both projects, compared the cost estimate for the TWF with best practices, and interviewed agency officials.

What GAO Recommends

GAO recommends that DOE revise the cost estimate for the TRU waste removal project to reflect the current understanding of project conditions and update the TWF's cost estimate to allow better management of the project's life-cycle costs going forward. DOE generally agreed with GAO's recommendations.

For more information, contact David C. Trimble at (202) 512-3841 or trimbled@gao.gov.

Recommendations for Executive Action

  1. Status: Open

    Comments: As of April 2017, Department of Energy (DOE) officials indicated that a revised life-cycle baseline cost estimate was prepared for all Office of Environmental Management mission work at Los Alamos National Laboratory, including transuranic waste removal work. DOE approved the revised cost estimate in July 2016. After we review documentation of the estimate, we will evaluate whether it is sufficient to close the recommendation.

    Recommendation: To develop reliable cost estimates for the TRU waste removal project and for the TWF construction project at LANL, the Secretary of Energy should direct NNSA and the Office of Environmental Management to revise the cost estimate for the TRU waste removal project to ensure that it uses updated assumptions based on the current understanding of project conditions, such as the status of WIPP.

    Agency Affected: Department of Energy

  2. Status: Open

    Comments: The Department of Energy (DOE) agreed with the recommendation. As of March 2017, DOE indicated that Los Alamos National Laboratory prepared a cost estimate for the operations and maintenance of the Transuranic Waste Facility (TWF) facility in December 2015, which was reviewed and accepted by the responsible program offices. DOE indicated that the revised estimate reflected operational costs for a seven-year window and incorporated applicable best practices, including documentation of any significant deviations and uncertainties impacting the estimate, among other things. After we obtain documentation of the estimate, we will evaluate the action to determine whether it is sufficient to close the recommendation as implemented.

    Recommendation: To develop reliable cost estimates for the TRU waste removal project and for the TWF construction project at LANL, the Secretary of Energy should direct NNSA to revise and update the TWF project's cost estimate by following all best practices for developing a reliable cost estimate that covers all life-cycle costs for better managing the project going forward.

    Agency Affected: Department of Energy

 

Explore the full database of GAO's Open Recommendations »

Nov 15, 2017

Nov 2, 2017

Oct 30, 2017

Oct 24, 2017

Oct 23, 2017

Oct 18, 2017

Oct 16, 2017

Oct 12, 2017

Oct 2, 2017

Sep 18, 2017

Looking for more? Browse all our products here