Suspension and Debarment:
DOD Has Active Referral Processes, but Action Needed to Promote Transparency
GAO-12-932, Sep 19, 2012
Additional Materials:
- Highlights Page:
- Accessible Text:
Contact:
(202) 512-8214
woodsw@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
The four Department of Defense (DOD) components GAO examined have active processes for referring identified cases of contractor misconduct for appropriate action, including suspension or debarment. The components identify numerous cases of actual or alleged contractor misconduct each year from various internal and external sources. The figure below shows the process for identifying and referring cases to the suspension and debarment official for consideration.
DOD received hundreds of leads on contractor misconduct from sources such as lawsuits against contractors or contractor disclosures in fiscal years 2009 through 2011, although it is not possible to know the full extent of potential leads. Some cases are referred to suspension and debarment officials for their consideration or to other agencies for further action. GAOs analysis of selected cases shows that DOD follows its procedures for identifying and referring cases involving contractor misconduct or poor performance for possible suspension and debarment.
Once a case is referred, DOD generally makes suspension and debarment decisions in accordance with the discretion provided by the Federal Acquisition Regulation (FAR). GAO found in reviewing 75 case files that DOD generally maintained adequate records, informed the contractor of the cause and rationale for its decisions, and provided notice of the action to the contractor as required by the FAR. Given the discretion provided by the FAR, suspension and debarment periods vary based on the circumstances of the case, as do the reasons for removing contractors from the suspension and debarment list. For example, the FAR provides that the period of debarment generally should not exceed 3 years, but notes that the debarment period must be for a period commensurate with the seriousness of the cause. GAO found that nearly half the contractors DOD debarred during fiscal years 2009 through 2011 had debarment periods that exceeded 3 years.
The FAR prohibits all agencies from doing business with suspended or debarred contractors unless there is a compelling reason for doing so. The four DOD components made 14 compelling reason determinations during fiscal years 2009 through 2011. In none of these cases, however, did the components provide notice of their compelling reason determinations to the General Services Administration (GSA), as required by statute and regulation, until GAO raised this as an issue. Component officials said they were uncertain why these determinations which can promote transparency to the public were not forwarded to GSA.
Why GAO Did This Study
DOD spends more than any other federal agency on contracts for goods and services and must be able to protect itself from irresponsible contractors. Once a case of misconductsuch as fraudis identified, DOD can use suspensions and debarments to prevent irresponsible contractors from receiving new contracts. As requested, GAO determined (1) the extent to which DOD has processes for identifying and referring cases of contractor misconduct for possible suspension or debarment, and (2) how DOD makes suspension and debarment decisions once cases have been referred for potential action. GAOs review focused on four DOD componentsthe Departments of the Air Force, Army, Navy (including the U.S. Marine Corps), and Defense Logistics Agencywhich together took a total of 3,443 suspension and debarment actions during fiscal years 2009 through 2011, accounting for nearly 100 percent of all such actions in DOD. GAO reviewed DOD and component regulations, procedures, and policies; reviewed case files; analyzed information from federal databases; and interviewed DOD and component officials.
What GAO Recommends
GAO recommends that DOD ensure that DOD components are aware of and comply with the requirement to notify GSA when awarding contracts to suspended or debarred contractors based on compelling reason determinations. DOD concurred with this recommendation.
For more information, contact William T. Woods at (202) 512-4841 or woodsw@gao.gov.
Status Legend:
- Review Pending
- Open
- Closed - implemented
- Closed - not implemented
Recommendation for Executive Action
Recommendation: The Secretary of Defense should direct the Under Secretary of Defense for Acquisition, Technology, and Logistics to ensure that each DOD component is aware of and complies with the requirement to notify the GSA of determinations that a compelling reason exists to do business with a suspended or debarred contractor.
Agency Affected: Department of Defense
Status: Review Pending
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Jun 11, 2013
Defense Management
May 31, 2013
Defense Infrastructure
May 29, 2013
Human Capital
May 23, 2013
Defense Acquisitions
Defense Infrastructure
May 17, 2013
DOD Business Systems Modernization
May 16, 2013
Defense Management
May 15, 2013
Defense Headquarters
May 14, 2013
Defense Infrastructure
May 13, 2013
Defense Logistics
Looking for more? Browse all our products here







