Missile Defense:
Opportunity Exists to Strengthen Acquisitions by Reducing Concurrency
GAO-12-486, Apr 20, 2012
Additional Materials:
- Highlights Page:
- Accessible Text:
Contact:
(202) 512-3000
chaplainc@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
In fiscal year 2011, the Missile Defense Agency (MDA) experienced mixed results in executing its development goals and Ballistic Missile Defense System (BMDS) tests. For the first time in 5 years, GAO found that all of the targets used in this years tests were delivered and performed as expected. None of the programs GAO assessed were able to fully accomplish their asset delivery and capability goals for the year. Flight test failures, an anomaly, and delays disrupted the development of several components and models and simulations challenges remain. Flight test failures forced MDA to suspend or slow production of three out of four interceptors currently being manufactured while failure review boards investigated their test problems.
To meet the presidential 2002 direction to initially rapidly field and update missile defense capabilities as well as the 2009 announcement to deploy missile defenses in Europe, MDA has undertaken and continues to undertake highly concurrent acquisitions. Concurrency is broadly defined as the overlap between technology development and product development or between product development and production. While some concurrency is understandable, committing to product development before requirements are understood and technologies mature or committing to production and fielding before development is complete is a high-risk strategy that often results in performance shortfalls, unexpected cost increases, schedule delays, and test problems. It can also create pressure to keep producing to avoid work stoppages. In contrast, as shown in the notional graphic below, successful programs that deliver promised capabilities for the estimated cost and schedule use a disciplined knowledge-based approach.
High levels of concurrency were present in MDAs initial efforts and are present in current efforts, though the agency has begun emphasizing the need to follow knowledge-based development practices. During 2011, the Ground-based Midcourse Defense, the Aegis Standard Missile 3 Block IB, and the Terminal High Altitude Area Defense experienced significant ill effects from concurrency. For example, MDAs discovery of a design problem in a new variant of the Ground-based Midcourse Defense programs interceptors while production was underway increased costs, may require retrofit of fielded equipment, and delayed delivery. Flight test cost to confirm its capability has increased from $236 million to about $1 billion. Because MDA continues to employ concurrent strategies, it is likely that it will continue to experience these kinds of acquisition problems.
Why GAO Did This Study
MDA has spent more than $80 billion since its initiation in 2002 and plans to spend $44 billion more by 2016 to develop, produce, and field a complex integrated system of land-, sea-, and space-based sensors, interceptors, and battle management, known as the BMDS.
Since 2002, National Defense Authorization Acts have mandated that GAO prepare annual assessments of MDAs ongoing cost, schedule, testing, and performance progress. This report assesses that progress in fiscal year 2011. To do this, GAO examined the accomplishments of the BMDS elements and supporting efforts and reviewed individual element responses to GAO data collection instruments. GAO also reviewed pertinent Department of Defense (DOD) policies and reports, and interviewed a wide range of DOD, MDA, and BMDS officials.
What GAO Recommends
GAO makes seven recommendations to the Secretary of Defense to reduce concurrency and strengthen MDAs near- and long-term acquisition prospects. DOD concurred with six recommendations and partially concurred with one related to reporting on the cause of the Aegis BMD Standard Missile-3 Block IB test failure before committing to additional purchases. DOD did not agree to tie additional purchases to reporting the cause of the failure. DODs stated actions were generally responsive to problems already at hand, but did not consistently address implications for concurrency in the future, as discussed more fully in the report.
For more information, contact Cristina Chaplain at (202) 512-4841 or chaplainc@gao.gov.
Status Legend:
- Review Pending
- Open
- Closed - implemented
- Closed - not implemented
Recommendations for Executive Action
Recommendation: To reduce concurrency and strengthen MDAs near-term acquisition prospects for the Aegis BMD program, the Secretary of Defense should direct MDA to report to the Office of the Secretary of Defense and to Congress the root cause of the SM-3 Block IB developmental flight test failure, path forward for future development, and the plans to bridge production from the SM-3 Block IA to the SM-3 Block IB before committing to additional purchases of the SM-3 Block IB.
Agency Affected: Department of Defense
Status: Review Pending
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: To reduce concurrency and strengthen MDAs near-term acquisition prospects for the SM-3 Block IIB program, the Secretary of Defense should direct MDA to ensure that the SM-3 Block IIB requirements are defined and feasible and that the proposed design can meet those requirements within cost, schedule, and other system constraints by delaying the commitment to product development until the program completes a successful preliminary design review.
Agency Affected: Department of Defense
Status: Review Pending
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: To reduce concurrency and strengthen MDAs longer-term acquisition prospects, the Secretary of Defense should direct the Office of the Under Secretary of Defense for Acquisition, Technology and Logistics to review all MDA acquisitions for concurrency, and determine whether the proper balance has been struck between the planned deployment dates and the concurrency risks taken to achieve those dates.
Agency Affected: Department of Defense
Status: Review Pending
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: To reduce concurrency and strengthen MDAs longer-term acquisition prospects, the Secretary of Defense should direct the Office of the Under Secretary of Defense for Acquisition, Technology and Logistics to review and report to the Secretary of Defense the extent to which the capability delivery dates announced by the President in 2009 are contributing to concurrency in missile defense acquisitions and recommend schedule adjustments where significant benefits can be obtained by reducing concurrency.
Agency Affected: Department of Defense
Status: Review Pending
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: To reduce concurrency and strengthen MDA's near-term acquisition prospects for the Ground-based Midcourse Defense (GMD) program, the Secretary of Defense should direct MDA to demonstrate that the new Capability Enhancement -II (CE-II) interceptor design works as intended through a successful intercept flight test in the operational environment-Flight Test GMD (FTG)-06b-prior to making the commitment to restart integration and production efforts.
Agency Affected: Department of Defense
Status: Open
Comments: DOD concurred with the recommendation. Although MDA is planning on resuming manufacturing after a successful FTG-06b intercept flight test, the test has yet to occur and is experiencing delays. We will follow up after the completion of the test to determine if the decision to restart manufacturing occurred after a successful intercept flight test.
Recommendation: To reduce concurrency and strengthen MDA's near-term acquisition prospects for the GMD program, the Secretary of Defense should direct MDA to take appropriate steps to mitigate the effect of delaying the CE-II production restart until a successful intercept occurs. Specific consideration should be given by MDA to accelerating additional needed CE-I refurbishments.
Agency Affected: Department of Defense
Status: Open
Comments: DOD concurred with this recommendation. Although MDA is planning to accelerate additional CE-I refurbishments, these refurbishments are being delayed. The program has not been able to complete the planned refurbishments. We will follow up again next year.
Recommendation: To reduce concurrency and strengthen MDA's near-term acquisition prospects for the Aegis Ballistic Missile Defense (Aegis BMD) program, the Secretary of Defense should direct MDA to verify the Standard Missile-3 (SM-3) Block IB engagement capability through the planned three developmental flight tests before committing to additional production beyond those needed for developmental testing.
Agency Affected: Department of Defense
Status: Open
Comments: In providing comments on this report, the agency concurred with this recommendation but has not yet completed all actions necessary to implement it. Specifically, the agency has not yet completed the full series of flight tests needed.
Recommendation: To reduce concurrency and strengthen MDA's near-term acquisition prospects for the Aegis BMD program, the Secretary of Defense should direct MDA to report to the Office of the Secretary of Defense and to Congress the root cause of the SM-3 Block IB developmental flight test failure, path forward for future development, and the plans to bridge production from the SM-3 Block IA to the SM-3 Block IB before committing to additional purchases of the SM-3 Block IB.
Agency Affected: Department of Defense
Status: Open
Comments: In providing comments on this report, the agency partially concurred with this recommendation. Given the recent publication of this report, the agency has not been able to report to Congress all the information necessary to implement the recommendation.
Recommendation: To reduce concurrency and strengthen MDA's near-term acquisition prospects for the SM-3 Block IIB program, the Secretary of Defense should direct MDA to ensure that the SM-3 Block IIB requirements are defined and feasible and that the proposed design can meet those requirements within cost, schedule, and other system constraints by delaying the commitment to product development until the program completes a successful preliminary design review.
Agency Affected: Department of Defense
Status: Open
Comments: In providing comments on this report, the agency concurred with this recommendation. Given the recent publication of this report, the agency has not taken all actions necessary to implement this recommendation. We will follow up next year on whether the program has adjusted its schedule to hold the preliminary design review prior to the commitment to product development.
Recommendation: To reduce concurrency and strengthen MDA's longer-term acquisition prospects, the Secretary of Defense should direct the Office of the Under Secretary of Defense for Acquisition, Technology and Logistics to review all MDA acquisitions for concurrency, and determine whether the proper balance has been struck between the planned deployment dates and the concurrency risks taken to achieve those dates.
Agency Affected: Department of Defense
Status: Open
Comments: In providing comments on this report, the agency concurred with this recommendation. Given the recent publication of this report, we are unable to report on whether all MDA acquisitions will be reviewed for the proper balance between the planned deployment dates and the concurrency risks to achieve those dates. We will follow up next year on whether this review has occurred.
Recommendation: To reduce concurrency and strengthen MDAs near-term acquisition prospects for the Aegis Ballistic Missile Defense (Aegis BMD) program, the Secretary of Defense should direct MDA to verify the Standard Missile-3 (SM-3) Block IB engagement capability through the planned three developmental flight tests before committing to additional production beyond those needed for developmental testing.
Agency Affected: Department of Defense
Status: Review Pending
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: To reduce concurrency and strengthen MDAs near-term acquisition prospects for the GMD program, the Secretary of Defense should direct MDA to take appropriate steps to mitigate the effect of delaying the CE-II production restart until a successful intercept occurs. Specific consideration should be given by MDA to accelerating additional needed CE-I refurbishments.
Agency Affected: Department of Defense
Status: Review Pending
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: To reduce concurrency and strengthen MDA's longer-term acquisition prospects, the Secretary of Defense should direct the Office of the Under Secretary of Defense for Acquisition, Technology and Logistics to review and report to the Secretary of Defense the extent to which the capability delivery dates announced by the President in 2009 are contributing to concurrency in missile defense acquisitions and recommend schedule adjustments where significant benefits can be obtained by reducing concurrency.
Agency Affected: Department of Defense
Status: Open
Comments: In providing comments on this report, the agency concurred with this recommendation. Given the recent publication of this report, the agency has not completed the actions necessary to fulfill the recommendation. We will follow up next year on any review of the capability delivery dates and recommended schedule adjustments.
Recommendation: To reduce concurrency and strengthen MDAs near-term acquisition prospects for the Ground-based Midcourse Defense (GMD) program, the Secretary of Defense should direct MDA to demonstrate that the new Capability Enhancement -II (CE-II) interceptor design works as intended through a successful intercept flight test in the operational environmentFlight Test GMD (FTG)-06bprior to making the commitment to restart integration and production efforts.
Agency Affected: Department of Defense
Status: Review Pending
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Jun 19, 2013
Defense Contractors
F-35 Joint Strike Fighter
Jun 11, 2013
Defense Management
May 31, 2013
Defense Infrastructure
May 29, 2013
Human Capital
May 23, 2013
Defense Acquisitions
Defense Infrastructure
May 17, 2013
DOD Business Systems Modernization
May 16, 2013
Defense Management
May 15, 2013
Defense Headquarters
Looking for more? Browse all our products here







