Skip to main content

National Aeronautics and Space Administration: Acquisition Approach for Commercial Crew Transportation Includes Good Practices, but Faces Significant Challenges

GAO-12-282 Published: Dec 15, 2011. Publicly Released: Dec 15, 2011.
Jump To:
Skip to Highlights

Highlights

What GAO Found

NASA’s planned approach for acquiring U.S. commercial crew transportation faces significant challenges that could impact its success, although it includes some good acquisition practices. Specifically, NASA’s current funding level for its program is lower than anticipated and may not allow NASA to award multiple contracts, which is its key element for maintaining cost control by sustaining competition through all phases of its commercial crew transportation program. Moreover, the critical need to transport crew to the space station beginning in 2016 requires an aggressive program schedule that may not be attainable given NASA’s experiences with past government and commercial development efforts.

Among the good practices that NASA adopted in its planned approach is the use of firm-fixed-price, performance-based contracts for the remaining program phases. NASA also plans to define high-level requirements before it awards contracts, and expects to minimize chances for requirements changes by allowing contractors maximum flexibility in developing vehicles and systems that can meet their private sector business needs as well as NASA’s needs. In addition, NASA has established a new process for obtaining insight and providing oversight of contractor’s progress that will be in place when the next phase of contracts are awarded. The insight that NASA obtains needs to provide sufficient data for NASA to monitor the need to change course for the program, and provide sufficient lead time to purchase additional seats on the Russian Soyuz vehicle, if needed. Moreover, effective implementation is key to the success of any acquisition approach, as success cannot be attributed to any one aspect of it, such as contract type or oversight processes.

NASA’s current funding level is almost 50 percent less than the funding level it anticipated when developing its acquisition approach. As a result, NASA’s ability to execute its approach as currently planned is unlikely. For example, if NASA cannot maintain more than one contractor for its next phase of commercial crew development, its prospects for competition for subsequent phases are weakened. Although private investment is anticipated, without government investment the market alone may not continue to grow and provide more than one contractor that would be able to compete for subsequent phases. As a result, NASA could become dependent on one contractor for providing crew transportation services to the space station, which increases the risk that the government will pay more than anticipated as few or no competitors will exist to help control market prices.

Finally, the overall schedule for the commercial crew transportation program is aggressive and leaves little room for any potential delays, though experience in developing space flight systems both traditionally and commercially indicates that there is significant schedule risk. This risk is also heightened given the inexperience of some of the potential commercial providers. Moreover, the strategy does not make it clear when and how NASA would need to make a decision to purchase additional flights on the Russian Soyuz vehicle, should the schedule for commercial efforts slip or if the proposed systems are not successful. Given that the lead time for purchasing a flight on the Soyuz is 3 years, not having a decision point could create additional risks of having no access to the space station for an extended period of time.

Why GAO Did This Study

Following the recent retirement of the space shuttle, the National Aeronautics and Space Administration (NASA) lacks a domestic capability to send crew and cargo to the International Space Station. NASA has been funding private industry development of space transportation capabilities since 2005 with the intent of purchasing these services commercially. NASA’s commercial efforts to transport cargo are well under way, but its efforts to transport crew are in their infancy. The risks associated with transportation of crew are greater than its cargo efforts because human lives are at stake.

GAO is required by the NASA Authorization Act of 2010 to assess NASA’s strategy for acquiring commercial crew services. Specifically, GAO addressed how NASA’s planned approach for commercial crew services aligns with good acquisition practices and the challenges it faces in implementation. GAO reviewed NASA’s plan; compared it to good acquisition practices identified in prior GAO reports, regulations, and the elements required to be addressed in the act; and interviewed program officials to obtain further information on the approach.

Recommendations

Recommendations for Executive Action

Agency Affected Recommendation Status
National Aeronautics and Space Administration To continue to ensure that NASA's acquisition approach for commercial crew transportation services is reasonable in light of new appropriations, the Administrator of NASA should direct the Commercial Crew Program to reassess its approach for acquiring services before initiating its procurement process for the Integrated Design Contract (IDC) and subsequent phases.
Closed – Implemented
NASA evaluated a range of alternative approaches for its near term strategy based on the current budget environment, and determined that it needed to adjust its strategy to retain competition and permit the Agency to focus limited resources to support continued progress toward a commercial capability. Rather than moving forward with a firm-fixed price contract for integrated design phase as planned, NASA will support the design and development of commercial crew transportation systems through the use of funded Space Act Agreements. On August 3, 2012, NASA awarded three funded Space Act Agreements for this effort.
National Aeronautics and Space Administration To ensure that the United States has continued access to the space station if NASA's commercial crew efforts do not result in a capability within the intended time frame, the Administrator of NASA should direct the Commercial Crew Program to establish criteria by which it will assess the progress of its commercial providers to determine whether the purchase of additional seats on the Russian Soyuz vehicle is required beyond 2016 and set time frames by which the initial and subsequent decisions will need to be made.
Closed – Implemented
On February 6, 2015, NASA announced its intent to purchase seats on Soyuz for calendar year 2018 with rescue/return services extending through spring 2019. Consistent with our recommendation, NASA established criteria and a timeframe for determining whether the purchase of seats on Soyuz is needed. As specified in its announcement, such a decision is needed three years prior to when seats are needed, and the decision is based on whether a commercial vehicle will be available by the needed date. As such, the criteria is that a successful demonstration or acceptance of a commercial vehicle is expected before the seats would be needed. NASA is beginning the procurement for Soyuz seats for calendar year 2018 now, because the first commercially crewed flight test is not projected to occur until late in calendar year 2017 and the procurement process must begin now in 2015 to allow for the three-year lead time.

Full Report

GAO Contacts

Office of Public Affairs

Topics

AviationCommercial space activitiesCost and scheduleInternational space stationLaunch vehiclesPrivate sectorProcurementRisk managementSpace stationTransportation services