United Nations:

Renovation Still Scheduled for Completion in 2013, but Risk to Its Schedule and Cost Remain

GAO-09-870R: Published: Jul 30, 2009. Publicly Released: Jul 30, 2009.

Additional Materials:

Contact:

Terrell G. Dorn
(202) 512-3000
contact@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In 2008, the United Nations (UN) began construction associated with its Capital Master Plan (CMP) to renovate its headquarters complex in New York City. As the UN's host country and largest contributor, the United States has a substantial interest in the success of the CMP. In this requested update, GAO reviewed the following key areas: schedule, cost, funding, risk management, procurement, and oversight. To perform this work, GAO reviewed UN documents and met with officials from the CMP office and other UN departments. GAO also reviewed select CMP schedules to assess the extent to which they met best practices for scheduling contained in GAO's Cost Estimating and Assessment Guide. To assess oversight and monitoring, GAO reviewed UN documents and oversight reports and interviewed officials from the UN's Office of Internal Oversight Services and officials from the U.S. Department of State (State).

Schedule: Despite delays in starting construction, UN officials still expect to complete the project in 2013. The likelihood of meeting this date will be clearer once detailed schedules for the renovation work are finalized as part of the contracting process. Contracts have been awarded for the Temporary North Lawn Building and one of the six buildings to be renovated and contracts for two more buildings are expected to be signed later this year. The CMP's integrated master schedule and the subschedule GAO reviewed met, to some extent, most of nine scheduling best practices. The UN has not formally analyzed the risks to either schedule to quantify their potential impact on meeting the project's completion date. Cost: The CMP's estimated cost is $97.5 million over its $1.88 billion budget, down from $190 million over budget in April 2008. CMP officials are optimistic about further reducing the cost, in part because of the recent downturn in the economy. However, member states are considering whether to add up to $206.6 million in related costs to the CMP. This would include $186 million in associated costs, such as furniture and equipment, and $20.6 million for a secondary data center. Some of these related costs are currently being paid from the CMP budget. Funding: Member state payments are on track and CMP officials expect the payments to cover renovation expenditures through 2011. However, CMP officials project funding shortfalls in 2012 and 2013 if the current budget overrun is not resolved and the General Assembly decides that the $206.6 million for related costs will be absorbed into the existing CMP budget. Risk management: The CMP office and its management consultant continue to assess risks to the project, resulting in an annual risk register, which identifies risks and mitigating strategies. The ability of the CMP office to complete the project within the original budget of $1.88 billion and the timeliness of the contracting process remain high-risk areas. Procurement: The UN has awarded contracts for 8 of an expected 22 contracts to the construction manager. It also reviews the construction manager's subcontracting process. The CMP office expects U.S. workers to provide most of the on-site labor for the renovation. Oversight: OIOS continues to monitor the CMP, has issued reports, and plans annual reviews of security-related issues. According to OIOS, it has enough staff to perform the work. State also monitors the CMP.

Recommendation for Executive Action

  1. Status: Closed - Implemented

    Comments: In 2009, we reported that the United Nations (UN) began construction associated with its Capital Master Plan (CMP) to renovate its headquarters complex in New York City. We found that the CMP integrated master schedule and a subschedule met, to some extent, most of the best practices for scheduling contained in "GAO Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Capital Program Costs." In particular, among other issues, CMP officials had not performed a schedule risk analysis to quantify the potential impact on meeting the project's completion date. As the schedule affects project costs--costs generally increase the longer a project takes--assessing risks to the schedule and quantifying their impact is important to ensuring that the project is completed within the limits of the funds available. Moreover, having schedules that align with best practices can help ensure that they are as useful and informative as possible. Therefore, we recommended that the Secretary of State and the U.S. Permanent Representative to the United Nations work with other member states to direct the CMP office to implement our best practices for scheduling, to the extent practical. In commenting on our draft report, the Department of State (State) agreed that the CMP office should strive to implement scheduling best practices that will help them improve their management of the project by providing better information on the impact and risk of delays. In 2013, we confirmed that State officials conveyed the intent of our recommendation, to the extent practical, through appropriate diplomatic channels to the cognizant UN officials affecting the organization's control of the CMP. Informed by our 2009 report, the UN Advisory Committee on Administrative and Budgetary Questions issued a report in October 2009 on the CMP. The report emphasized the need for intensive coordination and consultation between the CMP office and all other key stakeholders throughout the renovation project in order to avoid schedule delays and resulting cost increases. The report recommended that the General Assembly--the UN's main deliberative and policymaking organization--request the Secretary-General to provide progress reports with more comprehensive and specific information on project delays, including their cost implications as well as actions to manage delays and cost risks. Subsequently, the General Assembly adopted a resolution that incorporated the recommendations of the Advisory Committee. As a result, UN member states should be more aware of the importance of controlling the schedule and related costs of the headquarters renovation project, which should lead to heightened oversight of the CMP's project management efforts.

    Recommendation: We recommend that the Secretary of State should work with other member states to direct the CMP office to implement the best practices for scheduling contained in our Cost Estimating and Assessment Guide, to the extent practical for the CMP.

    Agency Affected: Department of State

 

Explore the full database of GAO's Open Recommendations »

Nov 18, 2014

Nov 13, 2014

Oct 21, 2014

Sep 24, 2014

Sep 10, 2014

Sep 9, 2014

Aug 28, 2014

Jul 24, 2014

Looking for more? Browse all our products here