Capitol Visitor Center:
Update on Status of Project's Schedule and Cost as of May 22, 2008
GAO-08-811T, May 22, 2008
Additional Materials:
- Accessible Text:
Contact:
(202) 512-3000
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
This testimony is based on our review of schedules and financial reports for the CVC project and related records maintained by AOC and its construction management contractor, Gilbane Building Company; our observations on the progress of work at the CVC construction site; and our discussions with the CVC team (AOC and its major CVC contractors) and AOC's Chief Fire Marshal. We also reviewed AOC's construction management contractor's periodic schedule assessments, proposed change order log, and weekly reports on construction progress.
Since the April 15, 2008, CVC hearing, the project's construction and fire alarm acceptance testing have moved forward, and despite continued delays in certain CVC and expansion space work, AOC still believes that the project will be ready to open in November 2008. According to AOC's construction management contractor, in dollar terms, the overall CVC project remains 99 percent complete. However, risks to the project's schedule remain in several time-critical activities, including the fire alarm acceptance testing. Many punch list items also remain to be completed, and a steady number of proposed change orders have to be resolved. At this time, however, AOC does not expect the punch list items or the proposed change orders to affect the project's completion date.
Jun 12, 2013
Suspension and Debarment
Jun 6, 2013
Managing for Results
May 22, 2013
Government Efficiency and Effectiveness
May 16, 2013
Government Efficiency and Effectiveness
May 15, 2013
Strategic Sourcing
May 14, 2013
Data Center Consolidation
Apr 29, 2013
State and Local Governments' Fiscal Outlook
Apr 25, 2013
Federal Real Property
Office of National Drug Control Policy
Apr 23, 2013
Voters with Disabilities
Looking for more? Browse all our products here