Storm Water Pollution:

Information Needed on the Implications of Permitting Oil and Gas Construction Activities

GAO-05-240: Published: Feb 9, 2005. Publicly Released: Mar 14, 2005.

Additional Materials:

Contact:

John B. Stephenson
(202) 512-6225
contact@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

To prevent pollutants from entering storm water runoff, the Clean Water Act's National Pollutant Discharge Elimination System Storm Water Program requires controls for construction activities that disturb land. Phase I of this program requires permitting for construction activities that disturb 5 acres or more, while Phase II requires permitting for activities disturbing between 1 and 5 acres. The Environmental Protection Agency (EPA) extended the Phase II compliance date for discharges associated with oil and gas construction activities until March 2005 to analyze the impact of Phase II on the oil and gas industry. GAO was asked to provide information about oil and gas construction activities--such as well drilling and pipeline construction--affected by Phase I and likely to be affected by Phase II, as well as Phase II's financial and environmental implications.

A small fraction of total oil and gas construction activities have been permitted under Phase I of EPA's storm water program. Phase I storm water permit data for three of the six largest oil and gas producing states--Louisiana, Oklahoma, and Texas--showed that 433 construction activities were permitted under Phase I over the most recent 12 months for which data were available. About 70 percent, 304 of the 433, were oil and gas pipeline activities, most of which were much larger than the 5 acre criterion under Phase I. About 17 percent, 72 of the 433, were drilling activities. In comparison, these three states reported drilling an average of about 10,000 wells for each of the past 3 years. Industry must decide whether to seek permit coverage, and it has sought to have its drilling activities permitted on few occasions because it has determined that most drilling activity involves distinct projects that disturb less than 5 acres each. In states we reviewed, there were few reported compliance problems associated with oil and gas construction activities. While it appears that most oil and gas construction activities may have to be permitted under Phase II, the actual number of activities that could be affected is uncertain, and the financial and environmental implications are difficult to quantify. The oil and gas construction activities affected by the rule may lead to increased financial costs for the oil and gas industry and federal agencies implementing the rule. Many of the potential costs stem from meeting permit requirements to review the impact of construction activities on endangered species, although this impact would be site specific and difficult to quantify. Potentially offsetting these costs, the rule may lead to additional environmental protections that are difficult to quantify, such as decreased levels of sediment in water and benefits for endangered species and their habitat. After delaying implementation of this rule for oil and gas construction activities for 2 years to study the impact of Phase II, EPA is analyzing the impact but, as yet, has not quantified the number of activities affected or the potential financial and environmental implications.

Status Legend:

More Info
  • Review Pending-GAO has not yet assessed implementation status.
  • Open-Actions to satisfy the intent of the recommendation have not been taken or are being planned, or actions that partially satisfy the intent of the recommendation have been taken.
  • Closed-implemented-Actions that satisfy the intent of the recommendation have been taken.
  • Closed-not implemented-While the intent of the recommendation has not been satisfied, time or circumstances have rendered the recommendation invalid.
    • Review Pending
    • Open
    • Closed - implemented
    • Closed - not implemented

    Recommendation for Executive Action

    Recommendation: So that EPA may fully understand the implications of Phase II of its storm water rule prior to deciding whether the oil and gas industry should be subject to it, the EPA should complete its Phase II analysis before making any final decision. Furthermore, as a part of this analysis, the EPA should assess (1) the number of oil and gas sites impacted by the Phase II rule; (2) the costs to industry of compliance with the rule and whether these costs are solely attributable to the storm water rule; and (3) the environmental implications and benefits of the storm water rule, including, but not limited to, potential benefits for endangered species.

    Agency Affected: Environmental Protection Agency

    Status: Closed - Not Implemented

    Comments: EPA has not issued a formal response to GAO's recommendation in GAO-05-240 but expects to do so toward the end of CY 2005. After GAO issued its report, EPA extended the deadline for Phase II storm water permit coverage for oil and gas construction activity between 1 and 5 acres until June 12, 2006. EPA did so to allow itself additional time to complete its analysis of the impact of the rulemaking. Later, in August 2005, Congress passed the Energy Policy Act of 2005. Section 323 of this act modifies the Clean Water Act's definition of an oil and gas exploration and production activity to include oil and gas construction activities. Because the Clean Water Act mandates that EPA not require a storm water permit for oil and gas exploration and production activities, the change in the Energy Policy Act of 2005 would appear to exclude oil and gas construction activities from storm water permit coverage as well.

    Aug 11, 2014

    Jul 28, 2014

    Jul 16, 2014

    Jul 15, 2014

    Jul 9, 2014

    Jun 30, 2014

    Jun 16, 2014

    May 22, 2014

    May 21, 2014

    May 19, 2014

    Looking for more? Browse all our products here