Earlier Effective Monitoring of Alcohol Fuels Projects May Have Minimized Problems

EMD-82-42: Published: Apr 23, 1982. Publicly Released: Apr 23, 1982.

Additional Materials:

Contact:

James Duffus, III
(202) 512-7756
contact@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In response to a congressional request, GAO reviewed the Department of Energy's (DOE) system for monitoring alcohol fuels financial assistance projects.

The DOE system for monitoring alcohol fuels projects is effective, but it was put in place 7 months after some of the projects started. As a result, some projects were near completion before effective monitoring began. The system has been identifying and resolving problems but, in some cases, the problems were identified too late. Problems remained unsolved in five study projects, and these projects may be terminated after substantial portions of their funding have been spent. If the projects had been monitored from the time they started, some of the problems might have been resolved or action could have been taken to terminate the projects without a sizeable expenditure of funds. A similar situation could arise with future programs. DOE erroneously made advance payments to 24 alcohol fuels feasibility study grantees who were to be paid on a reimbursable basis. Five grantees voluntarily returned a total of $378,110. However, grantees had spent the balance of the funds by the time the errors were detected. Had the monitoring system been in place, DOE could have detected the errors sooner and taken action to have more advances returned. By making erroneous advances, DOE lost oversight and control over the projects which might have also contributed to the problems. Since 60 percent of the award amount was erroneously advanced and not returned for 19 grants, project monitors were not afforded an opportunity to review billing vouchers. If an audit of the projects which received the erroneous advances shows that funds were misused, DOE should expand the audit.

Recommendation for Executive Action

  1. Status: Closed - Implemented

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The Secretary of Energy should: (1) require program offices to certify to appropriate contracting officers that effective project monitoring will be ready to begin when projects start; and (2) require contracting officers to obtain such certifications before making project awards.

    Agency Affected: Department of Energy

 

Explore the full database of GAO's Open Recommendations »

Sep 14, 2016

Sep 8, 2016

Aug 11, 2016

Aug 9, 2016

Aug 4, 2016

Jul 15, 2016

Jul 14, 2016

Jun 20, 2016

Mar 3, 2016

Looking for more? Browse all our products here