[Protest of Navy Bid Rejection]
B-262147
Published: Jul 27, 1995. Publicly Released: Jul 27, 1995.
Skip to Highlights
Highlights
A firm protested the Navy's rejection of its bid as nonresponsive, contending that the Navy improperly rejected its bid for specifying a shorter bid acceptance period than the required 90-day period. GAO held that the Navy properly rejected the protester's bid as nonresponsive, since the bid contained two acceptance periods, one of which was shorter than the required period. Accordingly, the protest was dismissed.