[Protest of Army Bid Rejection]

B-260867: Apr 25, 1995

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Army's rejection of its bid, contending that: (1) it erroneously specified a shorter bid acceptance period than required because of a latent ambiguity in the solicitation; and (2) the Army should not have rejected its bid. GAO held that the: (1) solicitation's bid acceptance period was not ambiguous; and (2) Army properly rejected the protester's bid as nonresponsive. Accordingly, the protest was dismissed.

Nov 24, 2017

  • FEI Systems
    We deny the protest in part and dismiss it in part.
    B-414852.2

Nov 22, 2017

Nov 21, 2017

  • A-P-T Research, Inc.
    We deny the protest in part and dismiss the protest in part.
    B-414825,B-414825.2

Nov 20, 2017

Nov 16, 2017

  • HBI-GF, JV
    We deny the protest.
    B-415036
  • Epsilon Systems Solutions, Inc.
    We dismiss the protest because it raises a matter of contract administration over which we do not exercise jurisdiction.