[Protest of Interior Solicitation Cancellation]

B-260525: Mar 23, 1995

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested a Department of the Interior solicitation cancellation, contending that: (1) Interior did not act in good faith in cancelling the solicitation; and (2) it was entitled to reimbursement of its bid preparation costs. GAO held that the protester: (1) untimely filed its protest more than 10 working days after it knew its basis of protest; and (2) was not entitled to reimbursement of its bid preparation costs. Accordingly, the protest was dismissed and the claim was denied.