A firm protested an Environmental Protection Agency (EPA) contract award, contending that: (1) the awardee was not responsible; and (2) EPA failed to adequately evaluate the awardee's price proposal. GAO held that the protester: (1) did not provide a valid basis of protest; and (2) untimely filed its protest more than 10 days after it knew its basis of protest. Accordingly, the protest was dismissed.

Oct 13, 2017

Oct 12, 2017

Oct 11, 2017

  • Daekee Global Company, Ltd.
    We dismiss the protest because the protester has not established that it is an interested party.
    B-414899,B-414899.2

Oct 10, 2017

Oct 6, 2017

Oct 5, 2017