[Protest of Army Solicitation]

B-259480: Dec 2, 1994

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested an Army solicitation, contending that the specifications were too restrictive. GAO held that the protester untimely filed its protest more than 10 days after it learned of the Army's adverse action on its agency-level protest. Accordingly, the protest was dismissed.