[Protest of Navy Contract Award for Blasting Grit]

B-258849 Published: Dec 27, 1994. Publicly Released: Dec 27, 1994.
Jump To:
Skip to Highlights

Highlights

A firm protested a Navy contract award for abrasive blasting grit, contending that the awardee's product should not have been included on the qualified products list. GAO held that the protester untimely filed its protest more than 10 days after it learned of initial adverse action on its agency-level protest. Accordingly, the protest was dismissed.