[Protest of Army Contract Award for Integration and Systems Engineering Services]

B-258847: Nov 8, 1994

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested an Army contract award for integration and systems engineering services, contending that the Army unreasonably evaluated its bid under two technical evaluation factors. GAO held that the: (1) protester's technical rating would not change even if it was given full credit for the two factors; and (2) protester was not sufficiently interested to protest the award, since it would not be line for award even if its protest were sustained. Accordingly, the protest was dismissed.