[Request for Reconsideration of Protest of USDA Contract Award]

B-258635.2: Jun 19, 1995

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm requested reconsideration of its dismissed protest of a Department of Agriculture contract award for copy center, mail room, and supply room operations. GAO had held that the awardee was able to meet the solicitation's personnel requirements. In its request for reconsideration, the protester contended that the previous decision was based on a material error of fact. GAO held that the protester did not submit any valid evidence to show that the decision was erroneous. Accordingly, the original decision was affirmed.