[Protest of Corps of Engineers Contract Award for Operation and Maintenance]

B-257293: May 24, 1994

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested an Army Corps of Engineers contract award for facility operation and maintenance, contending that the: (1) awardee made a material misrepresentation in its bid, since it planned to use a subcontractor other than the one it proposed to perform part of the contract; and (2) Corps should cancel the contract award. GAO held that the protester untimely filed its protest more than 10 days after it knew the basis of protest. Accordingly, the protest was dismissed.

Nov 22, 2017

Nov 21, 2017

  • A-P-T Research, Inc.
    We deny the protest in part and dismiss the protest in part.
    B-414825,B-414825.2

Nov 20, 2017

Nov 16, 2017

  • HBI-GF, JV
    We deny the protest.
    B-415036
  • Epsilon Systems Solutions, Inc.
    We dismiss the protest because it raises a matter of contract administration over which we do not exercise jurisdiction.