[Protest of Army Contract Award for Facilities Operation]

B-257256: Jun 16, 1994

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested an Army Corps of Engineers contract award for facilities operation and maintenance, contending that the Corps improperly made award without holding discussions. GAO held that the: (1) solicitation stated that award could be made without discussions; and (2) protester untimely filed its protest of alleged solicitation improprieties after bid opening. Accordingly, the protest was dismissed.