[Protest of DOE Subcontract Award for Wastewater Facility]

B-256557 Published: Jun 28, 1994. Publicly Released: Jun 28, 1994.
Jump To:
Skip to Highlights

Highlights

A firm protested a Department of Energy prime contractor's rejection of its bid for wastewater treatment facility construction, contending that the prime contractor unreasonably evaluated its technical proposal. GAO held that the protester untimely filed its protest more than 10 days after it knew the basis for its protest. Accordingly, the protest was dismissed.

Office of Public Affairs

Topics

Bid evaluation protestsBid rejection protestsConstruction contractsFederal procurementPrime contractorsTechnical proposal evaluationUntimely protests