[Claim for Protest Costs]

B-255273.2: Apr 12, 1994

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm claimed reimbursement for its protest costs pursuant to its protest under an Army solicitation. GAO held that the protester was not entitled to reimbursement of its protest costs, since the Army took corrective action within 2 weeks of the protest. Accordingly, the claim was denied.