Skip to main content

B-244660, Jul 10, 1991, 91-2 CPD ***

B-244660 Jul 10, 1991
Jump To:
Skip to Highlights

Highlights

PROCUREMENT - Sealed Bidding - Bids - Responsiveness - Certification Omission PROCUREMENT - Sealed Bidding - Terms - Materiality - Integrity certification DIGEST: Failure of bid to include signed certificate of procurement integrity is a material deficiency in the bid requiring that it be rejected as nonresponsive. Argument that certificate was not required because guaranteed minimum amount under indefinite quantity contract was less than $100. 000 is without merit where protester's bid was for more than $100. Quality was notified that its bid had been rejected as nonresponsive for that reason. Quality asserts that the rejection was improper because the requirement that a bidder submit a signed certificate with its bid does not apply to indefinite delivery contracts unless the total estimated value of orders eventually to be placed under the contract is expected to exceed $100.

View Decision

B-244660, Jul 10, 1991, 91-2 CPD ***

PROCUREMENT - Sealed Bidding - Bids - Responsiveness - Certification Omission PROCUREMENT - Sealed Bidding - Terms - Materiality - Integrity certification DIGEST: Failure of bid to include signed certificate of procurement integrity is a material deficiency in the bid requiring that it be rejected as nonresponsive; argument that certificate was not required because guaranteed minimum amount under indefinite quantity contract was less than $100,000 is without merit where protester's bid was for more than $100,000.

Attorneys

Quality Roofers & Guttering, Inc.:

Quality Roofers & Guttering, Inc. protests the rejection of its bid under invitation for bids (IFB) No. N62470-91-D-7449, issued by the Department of the Navy for indefinite quantity roof repairs at two Marine Corps installations. The agency determined Quality's bid nonresponsive for failure to include a signed certificate of procurement integrity. dismiss the protest.

The IFB contained the certificate of procurement integrity at Federal Acquisition Regulation (FAR) Sec. 52.203-8, required by the Office of Federal Procurement Policy (OFPP) Act, 41 U.S.C.A. Sec. 423(e)(1) (West Supp. 1990). Quality's bid did not include the certificate. On June 27, 1991, Quality was notified that its bid had been rejected as nonresponsive for that reason. Quality asserts that the rejection was improper because the requirement that a bidder submit a signed certificate with its bid does not apply to indefinite delivery contracts unless the total estimated value of orders eventually to be placed under the contract is expected to exceed $100,000, and the IFB here guaranteed only $50,000 of work.

Quality's argument is without merit. Its own bid of $547,835, apparently based on the Navy's estimated requirements, establishes that the total value of delivery orders expected to be placed under the contract exceeds $100,000, and that a signed certificate of procurement integrity is therefore required. A bidder's failure to complete the certificate is a material bid deficiency requiring that the bid be rejected as nonresponsive. Mid-East Contractors, Inc., B-242435, Mar. 29, 1991, 70 Comp.Gen. ***, 91-1 CPD Para. 342. Since Quality's bid did not contain the required certificate, the Navy properly rejected the bid as nonresponsive. See id.; FAR Sec. 14.404-2(m).

The protest is dismissed.

GAO Contacts

Office of Public Affairs