[Protests of Navy Contract Awards for Facility Construction]

B-234225,B-234227 Published: May 05, 1989. Publicly Released: May 05, 1989.
Jump To:
Skip to Highlights

Highlights

A firm protested two Navy contract awards for facility construction, contending that the Navy should have rejected the awardees' bids as nonresponsive, since their individual sureties were unacceptable. GAO held that: (1) the Navy properly found the awardees' bids responsive, since the bid bonds were superficially proper; and (2) it would not review the Navy's affirmative responsibility determinations. Accordingly, the protests were denied.

Office of Public Affairs

Topics

Bid bondsBid protest regulationsBid responsivenessBidder responsibilityConstruction contractsContract award protestsNaval procurementU.S. NavyProtests