B-226741, APR 23, 1987

B-226741 Apr 23, 1987
Jump To:
Skip to Highlights

Highlights

PROCUREMENT - CONTRACT MANAGEMENT - CONTRACT ADMINISTRATION - GAO REVIEW DIGEST: QUESTION OF WHETHER WORK UNDER SOLICITATION INSTEAD SHOULD BE ORDERED UNDER PROTESTER'S EXISTING CONTRACT IS A MATTER OF CONTRACT ADMINISTRATION NOT FOR REVIEW BY GENERAL ACCOUNTING OFFICE. MIDDLESEX CONTENDS THAT THE WORK COVERED BY THE RFQ IS ENCOMPASSED BY ITS CONTRACT NO. THE NAVY HAS DETERMINED THAT THE REPAIRS WERE NECESSITATED BY MIDDLESEX'S POOR WORKMANSHIP. MAINTAINING THAT THE CONCRETE REPAIRS WERE NECESSITATED BY A DEFICIENT CONCRETE MIX DESIGN FURNISHED BY THE NAVY. THAT THE NAVY THEREFORE IS LIABLE FOR THE DEFECTS. THEREFORE IS A MATTER OF CONTRACT ADMINISTRATION. SINCE ADMINISTERING AN EXISTING CONTRACT IS WITHIN THE DISCRETION OF THE CONTRACTING AGENCY.

View Decision

B-226741, APR 23, 1987

PROCUREMENT - CONTRACT MANAGEMENT - CONTRACT ADMINISTRATION - GAO REVIEW DIGEST: QUESTION OF WHETHER WORK UNDER SOLICITATION INSTEAD SHOULD BE ORDERED UNDER PROTESTER'S EXISTING CONTRACT IS A MATTER OF CONTRACT ADMINISTRATION NOT FOR REVIEW BY GENERAL ACCOUNTING OFFICE.

MIDDLESEX CONTRACTORS & RIGGERS, INC.:

MIDDLESEX CONTRACTORS & RIGGERS, INC., PROTESTS THE AWARD OF ANY CONTRACT UNDER REQUEST FOR QUOTATIONS (RFQ) NO. N62472-87-Q-2134, ISSUED BY THE DEPARTMENT OF THE NAVY FOR CONCRETE REPAIRS AT PORTSMOUTH NAVAL SHIPYARD, PORTSMOUTH, NEW HAMPSHIRE.

MIDDLESEX CONTENDS THAT THE WORK COVERED BY THE RFQ IS ENCOMPASSED BY ITS CONTRACT NO. N62472-84-C-1982, AND THAT THE NAVY THEREFORE SHOULD ORDER THE WORK FROM MIDDLESEX. THE NAVY HAS SOLICITED QUOTES ON THE WORK INSTEAD OF ALLOWING MIDDLESEX TO PERFORM IT BECAUSE, ACCORDING TO MIDDLESEX, THE NAVY HAS DETERMINED THAT THE REPAIRS WERE NECESSITATED BY MIDDLESEX'S POOR WORKMANSHIP. MIDDLESEX HAS APPEALED THE AGENCY'S DETERMINATION TO THE ARMED SERVICES BOARD OF CONTRACT APPEAL (BCA), MAINTAINING THAT THE CONCRETE REPAIRS WERE NECESSITATED BY A DEFICIENT CONCRETE MIX DESIGN FURNISHED BY THE NAVY, AND THAT THE NAVY THEREFORE IS LIABLE FOR THE DEFECTS.

WHETHER THE NAVY SHOULD ORDER THE WORK IN ISSUE FROM MIDDLESEX DEPENDS ON THE TERMS OF THE PARTIES' CONTRACT, AND THEREFORE IS A MATTER OF CONTRACT ADMINISTRATION. SINCE ADMINISTERING AN EXISTING CONTRACT IS WITHIN THE DISCRETION OF THE CONTRACTING AGENCY, WE WILL NOT REVIEW SUCH MATTERS. SEE BID PROTEST REGULATIONS, 4 C.F.R. SEC. 21.3(F)(1) (1986). MOREOVER, IT APPEARS TO US THAT THE RULING IN THE DISPUTE ALREADY BEFORE THE BCA LIKELY WILL RESOLVE THE ISSUE.

THE PROTEST IS DISMISSED.