B-223223, JUN 24, 1986, OFFICE OF GENERAL COUNSEL

B-223223 Jun 24, 1986
Jump To:
Skip to Highlights

Highlights

THE GAO HAS NO JURISDICTION TO REQUIRE SETTLEMENT OF AN UNPAID ACCOUNT BETWEEN A CONTRACTOR AND SUBCONTRACTOR BECAUSE THERE IS NO PRIVITY OF CONTRACT BETWEEN SUBCONTRACTORS AND THE UNITED STATES. IS THE ONLY PROTECTION THE GOVERNMENT PROVIDES FOR SUBCONTRACTORS SUPPLYING LABOR OR MATERIAL FOR A GOVERNMENT PROJECT AND WHO ARE UNABLE TO SETTLE AN UNPAID ACCOUNT WITH THE CONTRACTOR OR ITS SURETY. THE SUBCONTRACTOR MAY SUE TO ENFORCE COLLECTION UNDER THE PAYMENT BOND IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT IN WHICH THE CONTRACT WAS PERFORMED AND EXECUTED 90 DAYS AFTER THE LAST LABOR OR MATERIAL WAS FURNISHED. NO LATER THAN 1 YEAR AFTER THE DATE THE LAST LABOR OR MATERIAL WAS FURNISHED.

View Decision

B-223223, JUN 24, 1986, OFFICE OF GENERAL COUNSEL

GENERAL ACCOUNTING OFFICE - JURISDICTION - CONTRACTS - SUBCONTRACTORS' CLAIMS DIGEST: 1. THE GAO HAS NO JURISDICTION TO REQUIRE SETTLEMENT OF AN UNPAID ACCOUNT BETWEEN A CONTRACTOR AND SUBCONTRACTOR BECAUSE THERE IS NO PRIVITY OF CONTRACT BETWEEN SUBCONTRACTORS AND THE UNITED STATES. BONDS - PAYMENT - MILLER ACT COVERAGE - SUBCONTRACTORS, ETC. 2. THE MILLER ACT, 40, U.S.C. SEC. 270B (1982), IS THE ONLY PROTECTION THE GOVERNMENT PROVIDES FOR SUBCONTRACTORS SUPPLYING LABOR OR MATERIAL FOR A GOVERNMENT PROJECT AND WHO ARE UNABLE TO SETTLE AN UNPAID ACCOUNT WITH THE CONTRACTOR OR ITS SURETY. UNDER THE MILLER ACT, THE SUBCONTRACTOR MAY SUE TO ENFORCE COLLECTION UNDER THE PAYMENT BOND IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT IN WHICH THE CONTRACT WAS PERFORMED AND EXECUTED 90 DAYS AFTER THE LAST LABOR OR MATERIAL WAS FURNISHED, BUT NO LATER THAN 1 YEAR AFTER THE DATE THE LAST LABOR OR MATERIAL WAS FURNISHED.

MR. MARTIN J. WILLIS, PRESIDENT:

WHITE MOUNTAIN ELECTRIC, INC.

P.O. BOX 1037

GARDNERVILLE, NV 89410

WE REFER TO YOUR LETTER RECEIVED AT THE GENERAL ACCOUNTING OFFICE ON MAY 9, 1986 IN WHICH YOU, AS THE SUBCONTRACTOR ON THE CALIFORNIA 90-4 HOUSING AND URBAN DEVELOPMENT PROJECT, REQUEST OUR ASSISTANCE IN SECURING $16,000.00 OWED TO YOU FROM THE GENERAL CONTRACTOR, THE E.R. CUMMINS CONSTRUCTION CO., INC., FOR THE COMPLETION OF THE PROJECT'S ELECTRICAL CONSTRUCTION.

HOWEVER, THERE IS NO ACTION THAT WE CAN PROPERLY TAKE TO REQUIRE SETTLEMENT OF THE UNPAID ACCOUNT. THE SETTLEMENT OF OBLIGATIONS BETWEEN CONTRACTORS AND THOSE FURNISHING LABOR AND MATERIAL IS A MATTER OUTSIDE THE JURISDICTION OF OUR OFFICE, THERE BEING NO PRIVITY OF CONTRACT BETWEEN SUCH PERSONS AND THE UNITED STATES. SEE PYRAMID STONE CO., B-203736, JULY 31, 1981, 81-2 CPD PARA. 79, AND H.A. SACK CO., INC., B-203291, JUNE 15, 1981 81-1 CPD PARA. 489, AND CASES CITED THEREIN.

THE MILLER ACT PAYMENT BOND, 40 U.S.C. SEC. 270A (1982), IS THE ONLY PROTECTION PROVIDED BY THE GOVERNMENT FOR PERSONS SUPPLYING LABOR OR MATERIAL IN THE PROSECUTION OF THE WORK PROVIDED FOR IN A GOVERNMENT CONSTRUCTION CONTRACT. IN THE EVENT THAT A PERSON SUPPLYING LABOR OR MATERIAL IS UNABLE TO WORK OUT AN ADJUSTMENT OF AN UNPAID ACCOUNT WITH THE CONTRACTOR OR ITS SURETY, A SUIT TO ENFORCE COLLECTION UNDER THE PAYMENT BOND MAY BE BROUGHT UNDER THE MILLER ACT, 40 U.S.C. SEC. 270B (1982), IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT IN WHICH THE CONTRACT WAS PERFORMED AND EXECUTED 90 DAYS AFTER THE LAST LABOR OR MATERIAL WAS FURNISHED, BUT NO LATER THAN 1 YEAR AFTER THE DATE THE LAST LABOR OR MATERIAL WAS FURNISHED.