[Protest of GSA Rejection of Bid]

B-218407: Apr 4, 1985

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the General Services Administration's rejection of its bid as being nonresponsive, arguing that it should have been allowed to correct its bid errors. GAO noted that the protester had offered an acceptance period in its bid which was shorter than the required period in the solicitation. GAO held that such errors are material to a solicitation and cannot be corrected after bid opening. Accordingly, the protest was dismissed.

Nov 20, 2017

Nov 16, 2017

  • HBI-GF, JV
    We deny the protest.