B-200570, OCT 22, 1980

B-200570 Oct 22, 1980
Jump To:
Skip to Highlights

Highlights

AMP ARGUES THAT APOCALYPSE IS "NONRESPONSIVE" BECAUSE IT SUBMITTED A BELOW COST BID WHICH WILL NOT ALLOW APOCALYSE TO PERFORM THE CONTRACT IN A "COMPETENT MANNER WITHOUT OPERATING AT A LOSS OR COMMITTING WAGE OR LABOR VIOLATIONS.". WE HAVE HELD THAT THE SUBMISSION OF A BELOW COST BID IS NOT A PROPER BASIS UPON WHICH TO CHALLENGE THE VALIDITY OF A CONTRACT AWARD. THIS RULE APPLIES EVEN WHERE A CONTRACTOR MAY INCUR A LOSS IF WAGES AS SET OUT IN THE APPLICABLE WAGE DETERMINATION ARE PAID. " THIS IS CLEARLY A MATTER OF THE "RESPONSIBILITY" OF APOCALYPSE AND DOES NOT CONCERN THE RESPONSIVENESS OF THAT FIRM'S BID. REJECTION OF APOCALYPSE WOULD REQUIRE A DETERMINATION THAT THE BIDDER IS NONRESPONSIBLE OR INCAPABLE OF PERFORMANCE.

View Decision

B-200570, OCT 22, 1980

DIGEST: 1. ALLEGATION OF BELOW COST BID WHICH WOULD RESULT IN LOSS CONTRACT AND INABILITY TO PERFORM CONTRACT PROVIDES NO BASIS UPON WHICH AWARD MAY BE CHALLENGED. 2. GAO DOES NOT REVIEW AFFIRMATIVE DETERMINATION OF RESPONSIBILITY ABSENT CIRCUMSTANCES NOT PRESENT HERE.

AMERICAN MUTUAL PROTECTIVE BUREAU:

AMERICAN MUTUAL PROTECTIVE BUREAU (AMP) PROTESTS ANY AWARD OF A CONTRACT TO APOCALYPSE, INC. UNDER INVITATION FOR BIDS (IFB) NO. DAKF03 80-B-0054 ISSUED BY THE DEPARTMENT OF THE ARMY FOR SECURITY GUARD SERVICES AT FORT MACARTHUR, CALIFORNIA. AMP ARGUES THAT APOCALYPSE IS "NONRESPONSIVE" BECAUSE IT SUBMITTED A BELOW COST BID WHICH WILL NOT ALLOW APOCALYSE TO PERFORM THE CONTRACT IN A "COMPETENT MANNER WITHOUT OPERATING AT A LOSS OR COMMITTING WAGE OR LABOR VIOLATIONS." AMP ASKS THAT WE INVESTIGATE THIS SITUATION AND RULE ON THE MATTER.

WE HAVE HELD THAT THE SUBMISSION OF A BELOW COST BID IS NOT A PROPER BASIS UPON WHICH TO CHALLENGE THE VALIDITY OF A CONTRACT AWARD. INTER CON SECURITY SYSTEMS, INC., B-189165, JUNE 15, 1977, 77-1 CPD 434. THE PROCUREMENT REGULATIONS DO NOT PROVIDE FOR REJECTION OF SUCH BIDS AND THE FACT THAT A LOW BIDDER MAY INCUR A LOSS AT ITS BID PRICE DOES NOT JUSTIFY REJECTION OF AN OTHERWISE ACCEPTABLE BID. A.C. ELECTRONICS, INC., B-185553, MAY 3, 1976, 76-1 CPD 295. THIS RULE APPLIES EVEN WHERE A CONTRACTOR MAY INCUR A LOSS IF WAGES AS SET OUT IN THE APPLICABLE WAGE DETERMINATION ARE PAID. SEE, E.G., SIMCO ELECTRONICS, B-187152, AUGUST 31, 1976, 76-2 CPD 209.

IN THIS CONNECTION, WE DECLINE AMP'S REQUEST THAT WE INVESTIGATE ALLEGED POTENTIAL WAGE AND LABOR VIOLATIONS BY APOCALYPSE, SINCE THE DEPARTMENT OF LABOR, NOT THE GENERAL ACCOUNTING OFFICE, HAS THE RESPONSIBILITY FOR ADMINISTRATION AND ENFORCEMENT OF THE LABOR STATUTES INVOLVED IN THIS PROCUREMENT. SIMCO ELECTRONICS, SUPRA.

ALTHOUGH AMP CHARACTERIZES APOCALYPSE AS BEING "NONRESPONSIVE" BECAUSE OF AN ALLEGED LACK OF FINANCIAL CAPABILITY TO PERFORM A "LOSS CONTRACT," THIS IS CLEARLY A MATTER OF THE "RESPONSIBILITY" OF APOCALYPSE AND DOES NOT CONCERN THE RESPONSIVENESS OF THAT FIRM'S BID. IN THIS REGARD, REJECTION OF APOCALYPSE WOULD REQUIRE A DETERMINATION THAT THE BIDDER IS NONRESPONSIBLE OR INCAPABLE OF PERFORMANCE. SEE FUTRONICS INDUSTRIES, B-185896, MARCH 10, 1976, 76-1 CPD 169. HOWEVER, THIS OFFICE DOES NOT REVIEW PROTESTS WHICH QUESTION THE PROCURING AGENCY'S AFFIRMATIVE DETERMINATION OF RESPONSIBILITY EXCEPT IN CIRCUMSTANCES NOT PRESENT HERE. CENTRAL METAL PRODUCTS, INC., 54 COMP.GEN. 66 (1974), 74-2 CPD 64. FURTHERMORE, WE POINT OUT THAT IN THE INSTANT PROCUREMENT, WHICH IS A TOTAL SMALL BUSINESS SET-ASIDE, NO SMALL BUSINESS CONCERN MAY BE PRECLUDED FROM AWARD BECAUSE OF NONRESPONSIBILITY WITHOUT REFERRAL OF THE MATTER TO THE SMALL BUSINESS ADMINISTRATION FOR A FINAL DISPOSITION UNDER THE CERTIFICATE OF COMPETENCY PROCEDURE. 15 U.S.C. SEC. 637(B)(7) (SUPP. I, 1977).

BASED ON THE FOREGOING, FURTHER CASE DEVELOPMENT IS UNNECESSARY IN THIS INSTANCE SINCE IT IS CLEAR FROM AMP'S INITIAL SUBMISSION THAT THE ISSUES RAISED ARE NOT REVIEWABLE UNDER OUR BID PROTEST PROCEDURES. KURZ-KASCH, INC. - REQUEST FOR RECONSIDERATION, B-192604, OCTOBER 31, 1978, 78-2 CPD 311.

THE PROTEST IS DISMISSED.

GAO Contacts

Office of Public Affairs