Bid Not Accompanied by Requested Bid Guarantee Is Nonresponsive

B-194054 Feb 22, 1979
Jump To:
Skip to Highlights

Highlights

A firm protested the rejection of its bid. The protester failed to submit a bid guarantee prior to bid opening as required by the invitation for bids (IFB). The firm alleged that it did not submit a bid guarantee with its bid because an agency employee erroneously told the protester during a telephone conversation that the firm would have 60 days after bid opening in which to submit a bid guarantee. The protester's bid was rendered nonresponsive since the IFB required a bid guarantee and stated that oral explanations were not binding. The protest was without legal merit and was denied.

Downloads

GAO Contacts

Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel

Kenneth E. Patton
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries