Failure of Contracting Officer To Respond to Request for Contract Modification

B-193537: Dec 29, 1978

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A legal representative of a claimant, who states that he filed a request for a contract modification and the contracting officer appeared to be delaying in making a decision, requested information regarding the proper appeal procedure. The claimant and the legal representative were informed that GAO no longer reviews decisions rendered under the "Disputes" clause.