DIGEST: SBA REFUSAL TO GRANT PROTESTER LOAN OR ISSUE CERTIFICATE OF COMPETENCY ARE NOT MATTERS REVIEWABLE BY GAO UNDER BID PROTEST FUNCTION. CHALLENGES CERTAIN ACTIONS BY THE SBA WHICH HAVE ALLEGEDLY RESULTED IN THE LOSS OF A CONTRACT OPPORTUNITY UNDER BID NO. THEREFORE IS NOT FOR CONSIDERATION UNDER OUR BID PROTEST PROCEDURES (4 C.F.R.PART 20 (1978). SBA'S DENIAL OF A COC TO CELTECH IS ALSO NOT A MATTER SUBJECT TO REVIEW BY THIS OFFICE. OUR OFFICE WILL NOT REVIEW AN SBA DETERMINATION. THE PROTEST IS DISMISSED.

View Decision

B-193063, NOVEMBER 13, 1978

DIGEST: SBA REFUSAL TO GRANT PROTESTER LOAN OR ISSUE CERTIFICATE OF COMPETENCY ARE NOT MATTERS REVIEWABLE BY GAO UNDER BID PROTEST FUNCTION.

CELTECH:

THE PROTESTER, CELTECH, ALLEGEDLY A WHOLLY OWNED AND OPERATED MINORITY FIRM CERTIFIED BY THE SMALL BUSINESS ADMINISTRATION (SBA) 8(A) PROGRAM, CHALLENGES CERTAIN ACTIONS BY THE SBA WHICH HAVE ALLEGEDLY RESULTED IN THE LOSS OF A CONTRACT OPPORTUNITY UNDER BID NO. GSW-3FWR P2-80005. SBA DENIED BOTH CELTECH'S REQUEST FOR A LOAN NEEDED TO INCREASE WORKING CAPITAL AND INVENTORY AND A CERTIFICATE OF COMPETENCY (COC) NEEDED TO QUALIFY FOR A CONTRACT WITH THE GENERAL SERVICES ADMINISTRATION (GSA) WON BY COMPETITIVE BID.

SBA'S REFUSAL TO GRANT CELTECH A LOAN DOES NOT INVOLVE A PROCUREMENT BY OR FOR A FEDERAL AGENCY AND, THEREFORE IS NOT FOR CONSIDERATION UNDER OUR BID PROTEST PROCEDURES (4 C.F.R.PART 20 (1978). SEE DONOVAN CONSTRUCTION COMPANY, B-191721, MAY 12, 1978, 78-1 CPD 371. SBA'S DENIAL OF A COC TO CELTECH IS ALSO NOT A MATTER SUBJECT TO REVIEW BY THIS OFFICE. UNDER 15 U.S.C. SEC. 637(B)(7) (1976), AS AMENDED BY PUB. L. 95-89, 501, 91 STAT. 561, AUGUST 4, 1977, THE SBA HAS THE AUTHORITY TO ISSUE OR DENY A COC. OUR OFFICE WILL NOT REVIEW AN SBA DETERMINATION, REQUIRE ISSUANCE OF A COC, OR REQUIRE REOPENING OF A CASE WHEN A COC HAS BEEN DENIED. SEMCO, INC., B-192623, AUGUST 28, 1978, 78-2 CPD 147.

IN VIEW OF THE ABOVE, WE MUST DECLINE TO RULE ON THE MERITS OF THE PROTEST. ACCORDINGLY, THE PROTEST IS DISMISSED.