Skip to main content

Request for Contract Rescission because of Mistake in Bid

B-191630 Jun 08, 1978
Jump To:
Skip to Highlights

Highlights

A contractor requested that its contract be rescinded because of a mistake in the bid caused by a misunderstanding involving two different construction projects. Although the responsibility for preparation of a bid rests with the bidder, the Government estimate was in error, and the bidder was not asked to verify its price. The contract award was rescinded.

Downloads

GAO Contacts

Office of Public Affairs