Claim for Bid Preparation Costs Based on Improper Rejection of Late Bid

B-189345 Aug 01, 1978
Jump To:
Skip to Highlights

Highlights

A company claimed bid preparation costs in a previous decision because of the government's improper rejection of its bid as late. The decision to reject the bid was not arbitrary and capricious, but was based on a good faith interpretation of procurement regulations. The claim for bid preparation costs was denied.