Contract Is Renewable at Sole Discretion of Government
B-188043
Mar 07, 1977
Skip to Highlights
Highlights
The claimant protested the Army's decision not to exercise its option for grass cutting services. Under the option provisions, the contract is renewable at the Government's sole discretion, and GAO will not consider the contention that the agency should have exercised its contract option.