Modification of Contract Price Based Upon Contractor's Claim of Hardship

B-187441 Nov 12, 1976
Jump To:
Skip to Highlights

Highlights

Contractor requested modification of a GPO contract because of hardship. GAO lacks the authority to modify contract price based solely upon the contractor's claim of hardship. The request for modification due to alleged error was not allowed, as the contracting officer adequately discharged bid verification.