Highlights

The low bidder protested the rejection of its bid as nonresponsive, arguing that its bid was responsive because the solicitation did not require firm fixed-price bids, only firm fixed-price contracts. The notation inserted in the bid that the price was subject to freight charge increases rendered the bid nonresponsive according to the Armed Services Procurement Regulations.