Request for Reconsideration on the Basis of Unbalanced Bidding
B-186590
Nov 17, 1976
Skip to Highlights
Highlights
A company requested reconsideration of denial of its protest against GPO acceptance of a mathematically unbalanced bid. The allegation concerning cost data was untimely when first submitted, and the data referred to was never made part of the written protest. The decisions relied on by the protester did not demonstrate how this case comes within the general rule applied in unbalanced bidding cases.